Town of Watertown Building Inspector Kenneth Thompson will act as the OPM (owner's project manager) for the construction. Any questions, comments or concerns regarding this construction project should be emailed to him or he may be reached by telephone at 617-972-6480.
The latest construction news:
October 31, 2008
Desperini Contracting continues the reinforcing steel placement in partnership with L&L Concrete Forms who are actively constructing forms. C.F. Hasting
has begun backfilling the foundation at the rear of the building. The temporary electric service has been installed for the site. Slide show
October 27, 2008
L&L Concrete Forms made the second wall placement today of approximately 80 yards of concrete. Temporary electric wires are being hung to power the job site. C. F. Hastings is continuing to screen the excavated material and the initial phase of the new water main to the building was started. Slide show
October 21, 2008
Forming of the foundation walls continues. Slide show
October 20, 2008
L&L Concrete stripped parts of the first foundation walls placed on the 17th. Take a peek at the new walls.
October 17, 2008
L&L Concrete placed approximately 85 yards of concrete today in the first wall work. The iron workers continue tying rebar and form work continues as well. Pictures of the concrete placement are here.
October 8, 2008
L&L Concrete placed more footing concrete today. Framing of the foundation wall forms continues also. Pictures of today's activities may be viewed here.
October 7, 2008
L&L Concrete continues framing the footings and the form for the rear wall of the new building is being framed. Excavating contractor C.F. Hastings has stockpiled an impressive amount of soil on site from the basement. See the latest pictures here.
October 3, 2008
Concrete placement began this morning, L&L Concrete Forms are the contractor building the forms and placing the concrete. View a slide show of concrete placement in the first footings here.
October 2, 2008
Form work continues, concrete placement is imminent.
Older Links:
September 2008
August 2008
August 27, 2008 page, slide show
August 26, 2008 page, slide show
August 25, 2008 page, slide show
August 7-14, 2008
Link to July 2008 and earlier construction updates